Commissioning is where the work becomes the institution’s. Up to this point, the install is the integrator’s responsibility: the cable plant, the hardware, the configuration, the test results. After acceptance, the system is the institution’s: the cardholders, the recordings, the audit logs, the operational practice. The handover happens through a documented commissioning process that confirms every system performs against the design intent, every integration works, every record is in place, and the institutional staff can operate the system without the integrator on call. Get the commissioning right and the project closes cleanly; skip it and the institution holds the integrator on the project for months past substantial completion.

Pre-commissioning verification

When the verification applies

Before any system testing begins. The pre-commissioning checks confirm that the install is physically ready for testing: as-built drawings match the install, cable plant is certified, panel directories are complete, and the test instruments are calibrated.

The spec

Field note

CAN/ULC-S1001 integrated systems testing

When the standard applies

Every project where the security system interfaces with life-safety systems: fire alarm, voice evacuation, smoke control, sprinkler, elevator recall, magnetic lock release, access control release. CAN/ULC-S1001 governs the integrated test that confirms all systems work together during a fire event.

The spec

Field note

Per-system commissioning

When the checklist applies

Every security system on the project. The per-system commissioning verifies each system’s performance against design intent before the integrated systems testing and the institutional acceptance walkdown.

Cabling commissioning

Power and grounding commissioning

Access control commissioning

Video commissioning

Intrusion commissioning

Final acceptance walkdown

When the walkdown applies

After per-system commissioning is complete and the S1001 integrated test has been signed off. The acceptance walkdown is the institutional representatives’ physical walk of the entire install, confirming visual, functional, and operational standards are met.

The spec

Field note

Training delivery

When the training applies

At commissioning or shortly after, before the system goes into operational use by the institutional staff. Training is the handover that gives the institution the knowledge to operate the system independently.

The spec

Field note

Documentation handover

When the handover applies

At final acceptance. The documentation package is the institution’s reference for the system’s operational life: how it was designed, how it was installed, what it tested at, how it gets serviced.

The spec

Post-substantial-completion follow-up

When the follow-up applies

30 days, 90 days, and 1 year after substantial completion. The follow-up walkdowns address issues that emerge in operation but did not appear during commissioning.

The spec

Field note